Change Order / Variation Calculator
Calculate direct costs, overhead & profit (OH&P), bond markups, and cumulative contract sum adjustments under AIA A201 § 7 and FIDIC Clause 13.
Change Order Cost Inputs
Change Order Valuation
CO = 5.81% of ContractTotal Change Order Value
$58,075
Adjusted Contract Sum: $1,058,075
Direct Cost Subtotal:
$50,000
OH&P Markup Amount:
$7,500
Subtotal before Bond/Ins:
$57,500
Bond & Insurance Premium:
$575
Cumulative CO Impact:
5.81%
Change Order Cost Breakdown Tier Stack